What to Expect: A Week-by-Week Timeline of an ADU Build in Sacramento, CA
If you've been Googling "how long does it take to build an ADU in Sacramento," you've probably noticed the answers all over the place — some sites say three months, others say a year, and none of them really explain why . So let's break it down properly, the way we'd walk a client through it over coffee. An ADU build in Sacramento typically takes anywhere from 6 to 10 months from the day you sign your contract to the day you get your keys — and most of that time isn't even construction. It's paperwork, permits, and waiting on the county. Here's what actually happens, week by week. Weeks 1–3: Design and Planning This is where the project actually starts, even though no one's swinging a hammer yet. You'll meet with your contractor to talk through layout, square footage, finishes, and budget. If you're working with a design-build company, this is also when site measurements, soil checks, and utility locations get confirmed. By the end ...